prestressing_completed

Jui Creek Bridge in Navi Mumbai

 

 

Case Studies

Bridges constructed near urban centres and metropolitan cities become vulnerable to changes in alignment and levels etc.. Jui Creek Bridge is a link between Old Bombay and New Bombay which is growing fast. An important road passes under this bridge. The only remedy was to raise the decking of the bridge by 2.65 M.

 

The bridge consists of two simply supported spans of 44 M. length supporting two carriageways each of 7.3 M. width, two footpaths and central verge of 1.2 M. Detailed inspection and study of design showed that the structure is in good condition and the stability of the bridge is not going to be affected by raising the deck level by 2.65 M. Temporary diversion of the traffic was arranged. Seven girders of each span weighing 1400 T. were lifted simultaneously by using hydraulic jacks. After completing desired lifting, the load was transferred on to the support system and abutments and pier were raised to the new level. The decking load was then transferred to new elastomeric bearings installed on the raised substructure.

 

This is a landmark project for improving the infrastructure around Bombay and was technically a challenging task.

FPCC LTD.
Tel : +91 22 4322 9500
Address : 6/B, 6th Floor, Sterling Centre, Dr.Annie Besant Road, Worli 400 018, Mumbai, India
Email: freyssinet@fpccindia.com
© FPCC LTD.

Freyssinet-India