prestressing_completed

Bangalore Metro

Key Facts

• FPCC Completed Bangalore Metro project in just 8 months

• Length of corridor was 1500m

• 37 Spans has been used in this project

• FPCC used 19K15 Prestressing System

• FPCC has used 275 MT High tension strands

• Project Status is in Progress

 

 

Case Studies

Projects: Bangalore Metro


Details: This bridge is located in Bangalore. The total length of flyover was 1.5k.m..The total number of segments was 584 nos and duration was 8 months. The 19K15 system was used.

 