Case Studies
Project: Signature Bridge, Wazirabad
Challenge: Sinking of wells was required for the construction of the bridge.
Solution: Freyssinet soil anchors with a capacity of 150 tonne were employed fro this purpose. Each anchor was taken 70 meter deep by pneumatic drilling rigs. The casing, too, was taken to that depth and was withdrawn completely during grouting. In all 24 wells with 8 anchors were executed in this manner.